🗓 Submission Timing Intelligence

When is the best month — and weekday — to submit your planning application? Real approval-rate + decision-speed data from 144,135 dated decisions across UK LPAs.

📅 Monthly breakdown per LPA 🏆 Best / worst windows ⚡ Decision-speed by month 🌍 National baseline for context
🏛️ By LPA 🗓 Best LPAs by Month
Narrow by type All types Householder Full / Major Outline Reserved Matters Listed Building Conservation Area Prior Approval Lawful Development Change of Use Tree Works / TPO Discharge Conditions Amendment / NMA

📊 Forest of Dean

Months below refer to when you submit, not when the decision lands. Each application is bucketed by its received_date month — but the approval rate measures the final outcome, whenever it landed (60-90 days later typically). The lag is already baked into the signal: "submit in December = 100% approval" already accounts for the fact that those decisions arrive in Feb/March. The month-by-month table below shows the lag explicitly so you can see the full cycle.

Best month to submit: August — apps submitted then end up with 100.0% approval (sample: 21 decisions). Avoid submitting in February (80.8% approval).
⚖️ What this council's headline is made of. 32.4% of its typed decisions are tree consents, condition discharges and amendments — consent administration that approves at 98.2%. On actual development decisions the approval rate is 91.3% (345 decisions), 6.9 points lower than the mixed figure.
Use the type chips above to filter to the application type you are actually making — and treat cross-council comparisons of the mixed number with care, since the mix depends on which source fed each council.
🏆 Best SUBMIT Month
August
Apps submitted then → 100.0% approval (21 decisions)
⚠️ Avoid SUBMITTING In
February
Apps submitted then → 80.8% approval (52 decisions)
⚡ Submit For Fastest Decision
July
Apps submitted then → avg 57 days to decision
🎯 Inverse view — "I want a decision in [month], when do I submit?"

Based on this LPA's typical decision-lag of 112 days (~4 months), the table below shows when to submit if you want your decision to land in a specific month.

If you want a decision in...Submit by (approx.)That submit month's approval rate
Jan Submit by end of Sep 93.3%
Feb Submit by end of Oct 95.2%
Mar Submit by end of Nov 92.1%
Apr Submit by end of Dec 93.8%
May Submit by end of Jan 94.4%
Jun Submit by end of Feb 80.8%
Jul Submit by end of Mar 95.5%
Aug Submit by end of Apr 90.5%
Sep Submit by end of May 95.6%
Oct Submit by end of Jun 94.1%
Nov Submit by end of Jul 98.3%
Dec Submit by end of Aug 100%

Inverse calculation is approximate — actual decision time varies (range typically ±30 days). Use the Decision Time Predictor for tighter forecasts.

⏱ Decision speed by application type

How long different application types actually take at Forest of Dean. Householder apps are statutorily 8 weeks; full/major are 13 weeks — but the real numbers usually drift. This is what the data says, not what the statute says.
→ Fastest: Tree Works / TPO (34 days). Slowest: Heritage / LB (107 days).

Application type Decisions Approval rate Avg days Range
Full / Major 269 92.9% 97 d (14 wk) 31–364 d Filter ▸
Tree Works / TPO 78 97.4% 34 d (5 wk) 11–57 d Filter ▸
Discharge Conditions 60 98.3% 63 d (9 wk) 27–248 d Filter ▸
Amendment / NMA 20 100% 50 d (7 wk) 6–164 d Filter ▸
Heritage / LB 14 92.9% 107 d (15 wk) 55–298 d Filter ▸
Conservation Area (low sample) 7 100% 29 d (4 wk) 28–31 d Filter ▸
Advertisement (low sample) 5 100% 74 d (11 wk) 50–141 d Filter ▸
Listed Building (low sample) 2 50% 51 d (7 wk) 47–55 d Filter ▸
🤔
Submit-now-or-wait recommendation
BORDERLINE
Current month (November): 92.1% approval. Best (August): 100%. Best is too far away — submit now.
Current month's decision speed: ~61 days avg.

📅 Month-by-month breakdown — full submit→decide cycle

Each row shows the complete journey for applications received in that month: how long they took, when the decision actually landed, and what % were approved. The approval rate already accounts for everything that happens between submission and decision — the lag is part of the signal.

Submit month Decisions Approval rate Median lag Decision typically lands in Range
January 18
94.4%
106d (~15wk) → May 64–225d
February 52
80.8%
76d (~11wk) → May 51–201d
March 44
95.5%
95d (~14wk) → June 20–364d
April 21
90.5%
115d (~16wk) → August 19–143d
May 45
95.6%
93d (~13wk) → August 56–223d
June 102
94.1%
60d (~9wk) → August 28–209d
July 60
98.3%
57d (~8wk) → September 6–269d
August 21
100%
69d (~10wk) → October 9–350d
September 30
93.3%
81d (~12wk) → December 27–332d
October 63
95.2%
59d (~8wk) → December 27–298d
November 38
92.1%
61d (~9wk) → January 23–259d
December 16
93.8%
162d (~23wk) → May 11–268d

Read across each row: submit in [month] → wait [median lag] → decision lands in [target month] → outcome [approval rate]. The approval rate is the final outcome of the whole cycle, not a snapshot.

🗓 Day-of-week patterns

Day receivedDecisionsApproval rateAvg days
Monday 142 95.1% 83
Tuesday 104 85.6% 87
Wednesday 97 94.8% 75
Thursday 87 93.1% 88
Friday 89 97.8% 83
⚖️ Why timing matters less than they pretend: A planning decision should be made on its substantive merits, not the season. But officers have queues, committees have schedules, and consultees go on holiday. The data is a guide to operational friction, not policy friction. If your scheme is sound, time it to land in their best window. If it's borderline, give yourself every advantage.
📊 Data sources & freshness

Timing is a tactical edge, not strategic justification. Use alongside the constraint check + pattern fingerprint to make the case strong on substance, then time it to land well.

  • planning_applications.received_date (updated Daily ingest)
    144,135 dated decisions where a submission date and a decision are both known. The submission date is received_date, falling back to validated_date — many council portals publish only the validated date, and the statutory clock runs from it. Approval = approved/granted/permit. Sample size gating: months with fewer than 8 decisions excluded from best/worst recommendation.
  • Day-of-week patterns
    Reflects when applicants choose to submit, which may correlate with applicant type (Monday = professional consultants; Friday = end-of-week DIY submissions). Causality is correlative not causal.
  • Decision-time outliers
    Months showing 200+ day averages are flagged — they reflect older PINS-appeal-derived rows where determinations stretched over many months. Read the Jan/Feb/Nov/Dec numbers (largest samples) as the reliable benchmark.