💡 Submission Timing works best inside your planning journey — open or create your case there and your documents and site data fill this in for you.

🗓 Submission Timing Intelligence

When is the best month — and weekday — to submit your planning application? Real approval-rate + decision-speed data from 144,135 dated decisions across UK LPAs.

📅 Monthly breakdown per LPA 🏆 Best / worst windows ⚡ Decision-speed by month 🌍 National baseline for context
🏛️ By LPA 🗓 Best LPAs by Month
Narrow by type All types Householder Full / Major Outline Reserved Matters Listed Building Conservation Area Prior Approval Lawful Development Change of Use Tree Works / TPO Discharge Conditions Amendment / NMA

📊 Doncaster

Months below refer to when you submit, not when the decision lands. Each application is bucketed by its received_date month — but the approval rate measures the final outcome, whenever it landed (60-90 days later typically). The lag is already baked into the signal: "submit in December = 100% approval" already accounts for the fact that those decisions arrive in Feb/March. The month-by-month table below shows the lag explicitly so you can see the full cycle.

Best month to submit: August — apps submitted then end up with 98.4% approval (sample: 62 decisions). Avoid submitting in May (87.0% approval).
⚖️ What this council's headline is made of. 26.2% of its typed decisions are tree consents, condition discharges and amendments — consent administration that approves at 95%. On actual development decisions the approval rate is 91.3% (796 decisions), 3.7 points lower than the mixed figure.
Use the type chips above to filter to the application type you are actually making — and treat cross-council comparisons of the mixed number with care, since the mix depends on which source fed each council.
🏆 Best SUBMIT Month
August
Apps submitted then → 98.4% approval (62 decisions)
⚠️ Avoid SUBMITTING In
May
Apps submitted then → 87.0% approval (177 decisions)
⚡ Submit For Fastest Decision
June
Apps submitted then → avg 49 days to decision
🎯 Inverse view — "I want a decision in [month], when do I submit?"

Based on this LPA's typical decision-lag of 68 days (~2 months), the table below shows when to submit if you want your decision to land in a specific month.

If you want a decision in...Submit by (approx.)That submit month's approval rate
Jan Submit by end of Nov 98.2%
Feb Submit by end of Dec 90.9%
Mar Submit by end of Jan 93.8%
Apr Submit by end of Feb 92.4%
May Submit by end of Mar 93.1%
Jun Submit by end of Apr 89.6%
Jul Submit by end of May 87%
Aug Submit by end of Jun 93.4%
Sep Submit by end of Jul 92.9%
Oct Submit by end of Aug 98.4%
Nov Submit by end of Sep 91.5%
Dec Submit by end of Oct 95.3%

Inverse calculation is approximate — actual decision time varies (range typically ±30 days). Use the Decision Time Predictor for tighter forecasts.

⏱ Decision speed by application type

How long different application types actually take at Doncaster. Householder apps are statutorily 8 weeks; full/major are 13 weeks — but the real numbers usually drift. This is what the data says, not what the statute says.
→ Fastest: Tree Works / TPO (24 days). Slowest: Discharge Conditions (79 days).

Application type Decisions Approval rate Avg days Range
Full / Major 658 92.4% 66 d (9 wk) 20–343 d Filter ▸
Discharge Conditions 143 93% 79 d (11 wk) 2–301 d Filter ▸
Tree Works / TPO 81 100% 24 d (3 wk) 0–126 d Filter ▸
Amendment / NMA 58 93.1% 60 d (9 wk) 5–246 d Filter ▸
Advertisement 27 96.3% 58 d (8 wk) 23–175 d Filter ▸
Heritage / LB (low sample) 5 100% 74 d (11 wk) 34–125 d Filter ▸
🚀
Submit-now-or-wait recommendation
SUBMIT NOW
Current approval rate is 98.2% — only 0.2pp below the best month. Not worth waiting.
Current month's decision speed: ~62 days avg.

📅 Month-by-month breakdown — full submit→decide cycle

Each row shows the complete journey for applications received in that month: how long they took, when the decision actually landed, and what % were approved. The approval rate already accounts for everything that happens between submission and decision — the lag is part of the signal.

Submit month Decisions Approval rate Median lag Decision typically lands in Range
January 64
93.8%
66d (~9wk) → March 3–205d
February 79
92.4%
57d (~8wk) → April —
March 87
93.1%
66d (~9wk) → May 1–361d
April 77
89.6%
73d (~10wk) → June —
May 177
87%
66d (~9wk) → July —
June 136
93.4%
49d (~7wk) → August —
July 127
92.9%
53d (~8wk) → September —
August 62
98.4%
54d (~8wk) → October 1–292d
September 71
91.5%
64d (~9wk) → November —
October 86
95.3%
71d (~10wk) → December —
November 57
98.2%
62d (~9wk) → January 1–258d
December 66
90.9%
74d (~11wk) → February 3–246d

Read across each row: submit in [month] → wait [median lag] → decision lands in [target month] → outcome [approval rate]. The approval rate is the final outcome of the whole cycle, not a snapshot.

🗓 Day-of-week patterns

Day receivedDecisionsApproval rateAvg days
Monday 233 91.8% 85
Tuesday 233 93.6% 79
Wednesday 213 90.6% 72
Thursday 215 93% 68
Friday 220 91.8% 72
⚖️ Why timing matters less than they pretend: A planning decision should be made on its substantive merits, not the season. But officers have queues, committees have schedules, and consultees go on holiday. The data is a guide to operational friction, not policy friction. If your scheme is sound, time it to land in their best window. If it's borderline, give yourself every advantage.
📊 Data sources & freshness

Timing is a tactical edge, not strategic justification. Use alongside the constraint check + pattern fingerprint to make the case strong on substance, then time it to land well.

  • planning_applications.received_date (updated Daily ingest)
    144,135 dated decisions where a submission date and a decision are both known. The submission date is received_date, falling back to validated_date — many council portals publish only the validated date, and the statutory clock runs from it. Approval = approved/granted/permit. Sample size gating: months with fewer than 8 decisions excluded from best/worst recommendation.
  • Day-of-week patterns
    Reflects when applicants choose to submit, which may correlate with applicant type (Monday = professional consultants; Friday = end-of-week DIY submissions). Causality is correlative not causal.
  • Decision-time outliers
    Months showing 200+ day averages are flagged — they reflect older PINS-appeal-derived rows where determinations stretched over many months. Read the Jan/Feb/Nov/Dec numbers (largest samples) as the reliable benchmark.
Ask Planning Agent
🧭Guide me