🗓 Submission Timing Intelligence

When is the best month — and weekday — to submit your planning application? Real approval-rate + decision-speed data from 144,156 dated decisions across UK LPAs.

📅 Monthly breakdown per LPA 🏆 Best / worst windows ⚡ Decision-speed by month 🌍 National baseline for context
🏛️ By LPA 🗓 Best LPAs by Month
Narrow by type All types Householder Full / Major Outline Reserved Matters Listed Building Conservation Area Prior Approval Lawful Development Change of Use Tree Works / TPO Discharge Conditions Amendment / NMA

📊 Chorley

Months below refer to when you submit, not when the decision lands. Each application is bucketed by its received_date month — but the approval rate measures the final outcome, whenever it landed (60-90 days later typically). The lag is already baked into the signal: "submit in December = 100% approval" already accounts for the fact that those decisions arrive in Feb/March. The month-by-month table below shows the lag explicitly so you can see the full cycle.

Best month to submit: June — apps submitted then end up with 100.0% approval (sample: 12 decisions). Avoid submitting in September (93.8% approval).
⚖️ What this council's headline is made of. 19.9% of its typed decisions are tree consents, condition discharges and amendments — consent administration that approves at 92.4%. On actual development decisions the approval rate is 88.1% (581 decisions), 4.3 points lower than the mixed figure.
Use the type chips above to filter to the application type you are actually making — and treat cross-council comparisons of the mixed number with care, since the mix depends on which source fed each council.
🏆 Best SUBMIT Month
June
Apps submitted then → 100.0% approval (12 decisions)
⚠️ Avoid SUBMITTING In
September
Apps submitted then → 93.8% approval (16 decisions)
⚡ Submit For Fastest Decision
August
Apps submitted then → avg 45 days to decision
🎯 Inverse view — "I want a decision in [month], when do I submit?"

Based on this LPA's typical decision-lag of 69 days (~2 months), the table below shows when to submit if you want your decision to land in a specific month.

If you want a decision in...Submit by (approx.)That submit month's approval rate
Jan Submit by end of Nov 100%
Feb Submit by end of Dec 66.7%
Mar Submit by end of Jan 100%
Apr Submit by end of Feb 100%
May Submit by end of Mar 100%
Jun Submit by end of Apr 100%
Jul Submit by end of May 85.7%
Aug Submit by end of Jun 100%
Sep Submit by end of Jul 100%
Oct Submit by end of Aug 100%
Nov Submit by end of Sep 93.8%
Dec Submit by end of Oct 80%

Inverse calculation is approximate — actual decision time varies (range typically ±30 days). Use the Decision Time Predictor for tighter forecasts.

⏱ Decision speed by application type

How long different application types actually take at Chorley. Householder apps are statutorily 8 weeks; full/major are 13 weeks — but the real numbers usually drift. This is what the data says, not what the statute says.
→ Fastest: Amendment / NMA (51 days). Slowest: Heritage / LB (141 days).

Application type Decisions Approval rate Avg days Range
Full / Major 364 90.7% 100 d (14 wk) 30–349 d Filter ▸
Tree Works / TPO 96 95.8% 63 d (9 wk) 14–201 d ✕ clear
Amendment / NMA 44 93.2% 51 d (7 wk) 13–189 d Filter ▸
Advertisement 16 100% 74 d (11 wk) 51–205 d Filter ▸
Heritage / LB 12 91.7% 141 d (20 wk) 55–293 d Filter ▸
Lawful Development (low sample) 6 33.3% 48 d (7 wk) 33–56 d Filter ▸
Discharge Conditions (low sample) 4 0% 162 d (23 wk) 143–185 d Filter ▸
Householder (low sample) 3 66.7% 90 d (13 wk) 55–159 d Filter ▸
Prior Approval (low sample) 2 50% 28 d (4 wk) 1–55 d Filter ▸
Listed Building (low sample) 1 0% 56 d (8 wk) 56–56 d Filter ▸

ⓘ Month-by-month stats above are filtered to Tree Works / TPO only. The table above always shows all types so you can compare.

🚀
Submit-now-or-wait recommendation
SUBMIT NOW
Current approval rate is 100% — only 0pp below the best month. Not worth waiting.
Current month's decision speed: ~86 days avg.

📅 Month-by-month breakdown — full submit→decide cycle

Each row shows the complete journey for applications received in that month: how long they took, when the decision actually landed, and what % were approved. The approval rate already accounts for everything that happens between submission and decision — the lag is part of the signal.

Submit month Decisions Approval rate Median lag Decision typically lands in Range
February 4
100%
55d (~8wk) → April 41–67d
March 3
100%
46d (~7wk) → May 45–46d
April 7
100%
83d (~12wk) → July 58–201d
May 7
85.7%
63d (~9wk) → July 34–87d
June 12
100%
83d (~12wk) → September 46–167d
July 13
100%
55d (~8wk) → September 14–138d
August 16
100%
45d (~6wk) → October 32–79d
September 16
93.8%
53d (~8wk) → November 16–73d
October 5
80%
72d (~10wk) → December 44–99d
November 8
100%
86d (~12wk) → February 77–96d
December 3
66.7%
64d (~9wk) → February 57–72d

Read across each row: submit in [month] → wait [median lag] → decision lands in [target month] → outcome [approval rate]. The approval rate is the final outcome of the whole cycle, not a snapshot.

🗓 Day-of-week patterns

Day receivedDecisionsApproval rateAvg days
Monday 17 100% 52
Tuesday 18 88.9% 74
Wednesday 10 100% 63
Thursday 21 100% 65
Friday 23 100% 73
Saturday 6 83.3% 70
⚖️ Why timing matters less than they pretend: A planning decision should be made on its substantive merits, not the season. But officers have queues, committees have schedules, and consultees go on holiday. The data is a guide to operational friction, not policy friction. If your scheme is sound, time it to land in their best window. If it's borderline, give yourself every advantage.
📊 Data sources & freshness

Timing is a tactical edge, not strategic justification. Use alongside the constraint check + pattern fingerprint to make the case strong on substance, then time it to land well.

  • planning_applications.received_date (updated Daily ingest)
    144,156 dated decisions where a submission date and a decision are both known. The submission date is received_date, falling back to validated_date — many council portals publish only the validated date, and the statutory clock runs from it. Approval = approved/granted/permit. Sample size gating: months with fewer than 8 decisions excluded from best/worst recommendation.
  • Day-of-week patterns
    Reflects when applicants choose to submit, which may correlate with applicant type (Monday = professional consultants; Friday = end-of-week DIY submissions). Causality is correlative not causal.
  • Decision-time outliers
    Months showing 200+ day averages are flagged — they reflect older PINS-appeal-derived rows where determinations stretched over many months. Read the Jan/Feb/Nov/Dec numbers (largest samples) as the reliable benchmark.