Paragraph 38. Local planning authorities should approach decisions on proposed development in a positive and creative way. They should use the full range of planning tools available, including brownfield registers and permission in principle, and work proactively with applicants to secure developments that will improve the economic, social and environmental conditions of the area. Decision-makers at every level should seek to approve applications for sustainable development where possible.
Paragraph 39. Early engagement has significant potential to improve the efficiency and effectiveness of the planning application system for all parties. Good quality pre-application discussion enables better coordination between public and private resources and improved outcomes for the community.
Paragraph 40. Local planning authorities have a key role to play in encouraging other parties to take maximum advantage of the pre-application stage. They cannot require that a developer engages with them before submitting a planning application, but they should encourage take-up of any pre-application services they offer.
Paragraph 41. The more issues that can be resolved at pre-application stage, including the need to deliver improvements in infrastructure and affordable housing, the greater the benefits.
Paragraph 43. The right information is crucial to good decision-making, particularly where a proposal relates to the safeguarding of an asset and the level of detail should be proportionate to the assets importance and no more than is sufficient to understand the potential impact of the proposal on their significance.
Paragraph 44. Local planning authorities should publish a list of their information requirements for applications, which should be proportionate to the nature and scale of development proposals and reviewed on a frequent basis. Local planning authorities should only request supporting information that is relevant, necessary and material to the application in question.
Paragraph 47. Planning conditions should be kept to a minimum and only imposed where they are necessary, relevant to planning and to the development to be permitted, enforceable, precise and reasonable in all other respects. Agreeing conditions early is beneficial to all parties involved in the process and can speed up decision making. Conditions that are required to be discharged before development commences should be avoided, unless there is a clear justification.
Paragraph 48. Planning obligations should only be sought where they meet all of the following tests:
a) necessary to make the development acceptable in planning terms;
b) directly related to the development; and
c) fairly and reasonably related in scale and kind to the development.